RIVER WILL BE FINE, SAYS PRESIDENT WITH 11 DAYS LEFT IN OFFICE
The outgoing president issues a guarantee about the Huron River. The gallons-per-day figure that would back it up remains unpublished.
ANN ARBOR — "We will not have any negative impact on the Huron River," outgoing University of Michigan President Domenico Grasso said in a statement Thursday.1 His term ends November 30.2
The Daily wants to believe him, and went looking for the numbers that would let us.
What we found
The Textile Road site sits beside the Huron River.1,3 The University's FAQ says the facility won't draw from or discharge into the river, and that it is "reviewing designs to consider" closed-loop cooling.4,5 No gallons-per-day figure for water use has ever been published.5
All three parcels are recorded as Part 201 contamination "facilities" under state law. At 10221 Textile, the state lists lead in the groundwater above state criteria.3
The local water authority, YCUA, has a twelve-month moratorium on new water and sewer service to data centers, approved April 22, 2026.3
And on Thursday, the one regent who voted no cited, among other things, approving the project before environmental reviews.6
The Daily's position
A promise about a river should outlast the person who makes it. This one comes with a published expiration date for its author, and without the number that would let anyone check it.
The Receipts
Every factual statement above links to one of these. Quotation marks mean verbatim.
- Planet Detroit, "U-M Regents approve Los Alamos computing center," Nov. 2026
- YpsiDataCenter.org, "Not Yet: What the Regents Are Being Asked to Approve Thursday"
- YpsiDataCenter.org, U-M / Los Alamos Textile Road project page
- University of Michigan, LANL project FAQ
- YpsiDataCenter.org, "What They Said, and What the Record Shows"
- Samuel Dodge, "Max $785M budget approved for University of Michigan's Los Alamos facility near Ypsilanti," MLive, Nov. 19, 2026