Scale
RELATIVELY SMALL, SAYS REGENT OF 100-MEGAWATT FACILITY
Compared to a Ford plant, the computing center is petite. Compared to the definition of "hyperscale," less so.
ANN ARBOR — Size, as any physicist will tell you, depends on what you compare it to.
Regent Carl Meyers chose a Ford plant. "Though relatively small this building will sit on 20% of 124-acre site with approximately 240,000 square feet," he said, comparing it to the neighboring Rawsonville plant's reported 1.8 million square feet.1
Other things it could be compared to
- Power: the State filing totals 110 megawatts. A common industry threshold for "hyperscale" is 40.2
- Homes: at full load, about 2,640 megawatt-hours a day, roughly what 89,000 homes use.2
- The University's own current capacity: 3.5 megawatts, per President Grasso, at the same meeting.3
Meyers also said: "U of M will pay for the building of dedicated electric sub station that will ensure local service and bills are not impacted."1 The State filing described a new DTE substation with two-thirds of its capacity serving the project and a third for community benefit, against a $30 million capital contribution.2
The Daily agrees the building is smaller than a Ford plant. So is the Huron River.
The Receipts
Every factual statement above links to one of these. Quotation marks mean verbatim.